Canal Road Greenway

Poplar Road, BD18

We continued developing the seating area today after yesterday we completed digging out the area. The group installed the timber edging, laid the ground fabric and moved several tons of crush and run. We managed this despite each job going on at the same time and local people being confused about what was being constructed.

Today we were a group of 9.